Marañon Hydropower Plant CDM 6210

  • Start Year - End Year

    2023 - 2023

  • Direct Customer

    ECOSECURITIES

  • End Customer

    Compañía Eléctrica El Platanal S.A. (Celepsa)

  • Key words

    - Validation - Accompaniment
    - Hydroelectric

  • Geographic Scope

    Peru

  • State

    Completed

The objective of the contract is to facilitate the development and successful implementation of the Marañon Hydroelectric Power Plant CDM #6210, based on the following activities:

  • Development and submission to DOE of PDD revision for design review changes.
  • Elaboration of monitoring report ( 02/2017-12/2019 ), ER calculation and supporting evidence.
  • Submission to the DOE of RM and documentary support
  • Assistance in the submission of validation and verification reports to the DOE.
  • Responses to DOE and closure of Validation and Verification Reports
  • Accompanying the presentation to the CDM-EB for approval.